Track Renewal Kupferhammer + Level Crossing Maintenance

Track Renewal Kupferhammer + Level Crossing Maintenance

Romonta Unternehmensverbund

Track Renewal Kupferhammer + Level Crossing Maintenance

Client:Romonta Unternehmensverbund
Construction period:02/2020 - 05/2020
Executing company:    Rhomberg Sersa Deutschland GmbH
Contract value:approx. EUR 44,000

 

Project scope

  • Maintenance and inspection of WSSB-type level crossing throughout 2020
  • Comprehensive refurbishment of turnout 8

 

Leistungen Rhomberg Sersa Gleisbau GmbH

Level crossing works:

  • Inspection of level crossing type WSSB HS 64 b
  • Maintenance and inspection, including visual check of all components
  • Functional testing and evaluation
  • Preparation of inspection reports and action lists for potential defects


Turnout refurbishment (turnout 8):

  • Site setup (e.g. transport of ZWB and SKL trailers, small equipment, and necessary operating materials)
  • Replacement of turnout sleepers (turnout including end section dismantled and temporarily stored on site for sleeper renewal)
  • Reinstallation of turnout
  • Arc welding of 49E1 rail joints
  • Stress relief works
  • Restoration of edge/shunting path