St. Poelten Freight Corridor, Section 2

St. Poelten Freight Corridor, Section 2 ­ Permanent Way and Electrification Works

GZU Westabschnitt_Knoten Rohr_1

St. Poelten Freight Corridor, Section 2

Client:

ÖBB-Infrastruktur AG

Location:

Loosdorf - St. Poelten, Austria

Project time:

05/2015 - 04/2017

Executing companies::

Rhomberg Bahntechnik (consortium with Strabag Österreich AG)

Contract value:

14.83 Mio. € (percentage of consortium 60%)

 

The GZU JV ­ which is built­up of Rhomberg Bahntechnik and Strabag ­ got awarded for the construction works of approx. 2.8km of double­tracked HST line as part of the all­new freight line between Vienna and Salzburg.

The slab track is made of pre­fabricated 5.20m long sections of the OeBB­Porr­type, which in itself is classified as light spring­mass ­system.

Part of the project was also the installation of 2 high­speedturnouts with a 2.600m radius laid in concrete as well as the emergency water supply line along the Bruendlkapellentunnel, installation of the concrete walkways either side of the track and the installation of cable ducts.

Fact box:

  • 5.450m slab track of the OeBB ­Porr­system
  • 2 high­speed turnouts laid on concrete slab
  • 13.800m ballasted track including 7 turnouts
  • 1.300m² of noise absorption elements at the tunnel portals
  • 2.400m of noise absorption elements along the railway line (4­foot)
  • 5.400m walkways either side of the track
  • 1.550m emergency water supply line
  • 5.400m cable duct laid in concrete (tunnel)
  • 7.200m cable duct laid in ballast (open section)
  • 2.250m handrail in tunnel sections