Access Brenner North ­Lot A2

General contractor for the electrical and telecommunication infrastructure in the Lower Inn valley

Brenner_Zulaufstrecke Nord_Los A2_1

Access Brenner North ­Lot A2

Client:

ÖBB-Infrastruktur AG

Location:

Unterinntal, Austria

Project time:

12/2009 - 06/2012

Executing companies:

Rhomberg Bahntechnik (consortium with Deutsche Bahnbau GmbH)

Contract value (net):

40.00 Mio. € (percentage of consortium 50 %)

 

Rhomberg Bahntechnik GmbH, together with the German Federal Railway (Deutsche Bahn GmbH) are jointly responsible as general contractor for the electrical and telecommunication infrastructure contract in the Lower Inn valley. The contract was awarded by the Austrian Federal Railway Infrastructure department (Osterreichische Bundesbahn (OBB) Infrastruktur AG (GB Ul)).

The newly built railway line between Kundl and Baumkirchen in the Lower Inn valley in Austria, is a 41 kilometre double line track. The line consists of tunnels, U­boxes and other subsurface structures and connects to the future Brenner Base Tunnel, which forms part of the Munich­Verona (TEN1 BerlinPalermo) rail axis. The rail link will transport both passengers as well as freight. With trains travelling at speeds of up to 250km/h.