Weinsteige Tunnel W0543

Weinsteige Tunnel

Renewal of a 760 wooden turnout in the Weinsteige Tunnel.

SSB_Weinsteige

Weinsteige Tunnel

Client:Stuttgarter Straßenbahnen AG
Location:Stuttgart, Germany
Construction period:11/2019 - 12/2019
Executing company:    Rhomberg Sersa Gleisbau GmbH
Contract value: EUR 80,000

Project scope

  • Coordination of various trades and third parties
  • Measures for site setup and subsequent clearance
  • Construction site safety
  • Coordination of traffic safety and traffic management
  • Track construction works
  • Rail welding works
  • Disposal services

Services

  • Assembly of the new turnout at the SSB depot
  • Traffic safety measures
  • Dismantling of the old turnout into individual components and loading onto the client’s work train
  • Ballast removal down to formation level
  • Installation of turnout large components
  • Rail replacement in connection areas
  • Ballast backfilling of the turnout
  • Disposal of old superstructure materials
  • Subcontracted works: tamping of the turnout to final position, welding of rail joints
  • Truck transport to the installation site