Project Stuttgart 21, PFA 1.6 a, Los 3.4, Construction-time Diversion (BZU)

Projekt Stuttgart 21, PFA 1.6 a, Los 3.4, Construction-time Diversion (BZU)

Stuttgart 21

Projekt Stuttgart 21, PFA 1.6 a, Los 3.4, Construction-time Diversion (BZU)

Client:DB Projekt Stuttgart – Ulm GmbH
Location:Stuttgart, Germany
Construction period:04/2018 - 07/2019
Executing company:    Rhomberg Sersa Gleisbau GmbH
Contract value:approx. EUR 3.9 million

 

As part of Stuttgart 21, four tracks (two long-distance railway tracks and two S-Bahn tracks) were temporarily realigned by approx. 700 m each to create clearance for the tunnel portal of the new high-speed line Stuttgart – Ulm. The execution was carried out track by track during four main conversion closures.

Project scope

  • Lot 3.3: Retaining embankment
  • Lot 3.4: Superstructure BZU
  • Lot 3.5: New construction of railway bridge Imweg
  • Lot 3.6: Dismantling of pedestrian and cycle bridge

 

Services Rhomberg Sersa Gleisbau GmbH

Lot 3.4 Superstructure

  • 3,100 m new track construction
  • 775 m deep drainage
  • 712 m installation of cable trough, type III
  • Installation of approx. 11,000 t formation protective layer (PSS KG1)
  • Removal of approx. 12,000 t of old ballast
  • Removal and disposal of approx. 6,000 t of soil
  • Installation of approx. 3,000 m telecommunications cable