Horchheimer Tunnel
Infrastructure

Horchheim Tunnel

Due to its poor structural condition, the Horchheim Tunnel was completely closed whilst renovation work was carried out.

Reference datasheet

#Shortfacts

Location
Germany
Construction period
September 2023 – October 2023
Client
DB InfraGO AG
Contract value
502,000 euros

Our scope of work included the installation of new electrical power systems, tunnel safety lighting, the power supply at the south and north portals, the power connections to the signal boxes, and the electrical shaft heating systems.

To prevent frost damage, the drainage and flushing shafts of the tunnel drainage system are fitted with electric shaft heaters.

The heaters are fitted with water level monitoring and temperature control with integrated overheating protection.