Augustusburg Funicular Railway: Track Maintenance Measures

Augustusburg Funicular Railway: Track Maintenance Measures

Subproject Track Construction as part of the overall modernization of the Augustusburg Funicular Railway

Drahtseilbahn Augustusburg

Augustusburg Funicular Railway: Track Maintenance Measures

Client:Verkehrsverbund
Mittelsachsen GmbH
Location:Erdmannsdorf (Zschopautal),
Augustusburg, Deutschland
Construction period:09 - 12/2019
Executing company:    Rhomberg Sersa Deutschland GmbH
Contract value:EUR 207,000

Project scope

  • Track construction works
  • Rail logistics (sleepers, fastenings, ballast)
  • Determination of lifting and lining values using compensation method
  • Preparation of sleeper register

 

Services Rhomberg Sersa Gleisbau GmbH

  • Track surveying and staking out
  • Replacement of individual sleepers (removal of wooden sleepers, supply and installation of plastic sleepers)
  • Tamping and lining works along the entire route
  • Relocation of rail expansion devices
  • Stress relief and welding works
  • Repair of monolithic sleeper anchors
  • Replacement of defective fastenings
  • Profiling works
  • Restoration of shunting paths
  • Track construction works for the installation of a gas pipeline in open construction method