Augustusburg Funicular Railway: Track Maintenance Measures
Client: | Verkehrsverbund Mittelsachsen GmbH |
Location: | Erdmannsdorf (Zschopautal), Augustusburg, Deutschland |
Construction period: | 09 - 12/2019 |
Executing company: | Rhomberg Sersa Deutschland GmbH |
Contract value: | EUR 207,000 |
Project scope
- Track construction works
- Rail logistics (sleepers, fastenings, ballast)
- Determination of lifting and lining values using compensation method
- Preparation of sleeper register
Services Rhomberg Sersa Gleisbau GmbH
- Track surveying and staking out
- Replacement of individual sleepers (removal of wooden sleepers, supply and installation of plastic sleepers)
- Tamping and lining works along the entire route
- Relocation of rail expansion devices
- Stress relief and welding works
- Repair of monolithic sleeper anchors
- Replacement of defective fastenings
- Profiling works
- Restoration of shunting paths
- Track construction works for the installation of a gas pipeline in open construction method