Project Augustus Bridge
Client: | Hentschke Bau GmbH |
Location: | Dresden, Germany |
Construction period: | 04/2017 - 2021 |
Executing company: | Rhomberg Sersa Gleisbau GmbH |
Auftragsvolumen: | EUR 300,000 |
As part of the heritage restoration and flood damage repair of the Augustus Bridge in Dresden, the traffic and tram systems were comprehensively redeveloped. The scope of track construction works included the renewal of the overhead line, as well as the dismantling and reconstruction of road surfacing, track systems, electrical installations, and drainage systems.
Project scope
- Coordination of various trades and third parties
- Site setup and clearance
- Site safety measures
- Surveying services
- Marking works
- Track construction works
- Dismantling and reconstruction of drainage systems
- Civil engineering works for traction power, telecommunications, turnout, low-voltage, medium-voltage, and lightning protection systems
- Welding services (136 MF welds)
- Dismantling and reconstruction of all electrical connections
- Disposal services
Services
- Dismantling of sleeper track
- Construction of sleeper track and Slab Track type DVB AG, including associated works
- Dismantling and construction of 3 rail drainage connections
Subcontracted works
- Surveying services
- Track welding (136 MF welds)
- Dismantling and reconstruction of all electrical connections